Pre-removal Phase:

1. Identification and Assessment:

a. Hire a qualified asbestos assessor to conduct a thorough inspection and testing of the property. b. Analyze soil samples to determine the type and level of contamination.

2. Develop a Remediation Plan:

a. Based on the assessment, develop a comprehensive plan outlining the removal process, including safety protocols.

3. Regulatory Compliance:

a. Notify WorkSafe New Zealand and obtain the necessary approvals and permits for asbestos and contaminated soil removal. b. Ensure understanding and adherence to the Health and Safety at Work (Asbestos) Regulations 2016.

4. Assemble a Trained Team:

a. Hire trained and licensed personnel who are experienced in handling asbestos and contaminated soil.

5. Safety Precautions:

a. Equip the team with appropriate personal protective equipment (PPE). b. Set up safety barriers and warning signs to restrict access to the contaminated area.

Removal Phase:

6. Asbestos Removal:

a. Dampen the asbestos materials to minimize dust and fibers release. b. Carefully remove asbestos-containing materials following safety protocols. c. Package and label asbestos waste for proper disposal.

7. Contaminated Soil Excavation:

a. Use a digger to excavate the contaminated soil up to 400mm down. b. Ensure the safe handling and containment of the excavated soil to prevent cross-contamination. c. Load the soil onto trucks ensuring that it is covered and contained during transportation.

8. Transport to Approved Landfill:

a. Transport the contaminated soil and asbestos waste to a landfill approved for hazardous materials. b. Ensure that transportation follows the legal and safety requirements for hazardous waste.

Post-removal Phase:

9. Site Verification:

a. Collect and analyze soil samples from the excavated area to confirm the removal of contamination. b. Obtain a clearance certificate from a licensed assessor verifying the area is free from asbestos and contamination.

10. Restoration:
cssCopy code
a. Import clean soil to restore the excavated land to its original state. b. Replant vegetation or reconstruct structures as needed. 
11. Documentation and Reporting:
cssCopy code
a. Document the entire remediation process, including waste disposal records. b. Submit a report to WorkSafe and other relevant authorities. 
12. Monitoring:
cssCopy code
a. Regularly monitor the site for any potential recurrence of contamination. b. Develop a long-term plan to ensure the safety of the property. 

Note:

Ensure all activities are conducted following New Zealand's regulations and guidelines governing asbestos and contaminated soil management. Adapt and expand this action plan as per the specific requirements and conditions of the property.

Always prioritize the safety of workers, occupants, and the environment throughout the remediation process.